Categories
NCLEX EXAM
HESI ENTRANCE EXAM
HESI EXAM
ATI EXAM
NR & NUR Exams
Gizmos
AQA PAPERS AND MARK SCHEME
Exams and Certifications
NURS EXAM
PORTAGE LEARNING
NSG Exam
Ihuman Case Study
DMV
WGU EXAM
Study material
Quiz
Category
Tutor
Search
Login
Login
CLC 222 Module 1, 2, 3, 4, 5, 6 Exam Qs & As
Helpsheet
×
Helpsheet
×
Report question problem
×
I think the answer is wrong
There are multiple correct answers
There is a typing error
Image or comprehension text is not display properly
Something else(please specify below)
Any more information
Question Number 66
Cost reimbursement contracts are used when there is uncertainty in the outcome of the effort; the greatest risk is placed on the Government. Select the correct answer from the following statements:
Under a cost reimbursement contract, the contractor is reimbursed for all allowable, allocable, and reasonable cost incurred
✔ Correct Answer:
Under a cost reimbursement contract, the contractor is reimbursed for all allowable, allocable, and reasonable cost incurred